PURCHASER UPDATE
STAGE 1
STAGE 2
STAGE 3
STAGE 4
STAGE 5
STAGE 6
STAGE 7
COMPLETE
COMPLETE
100%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 100%
Sewer Works 100%
Water & Gas Reticulation 100%
Conduit and AGI Installation 100%
Pavement Works 100%
Kerb & Channeling 100%
Electrical & NBN 100%
Footpaths & Top Soiling 100%
Asphalting and Line-marking 100%
Intersection _ 100%
External services 100%
100%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 100%
Sewer Works 100%
Water & Gas Reticulation 100%
Conduit and AGI Installation 100%
Pavement Works 100%
Kerb & Channeling 100%
Electrical & NBN 100%
Footpaths & Top Soiling 100%
Asphalting and Line-marking 100%
Intersection 100%
External services 100%
90%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 100%
Sewer Works 100%
Water & Gas Reticulation 100%
Conduit and AGI Installation _ 100%
Pavement Works 100%
Kerb & Channeling _100%
Electrical & NBN 100%
Footpaths & Top Soiling _ 90%
Asphalting and Line-marking 50%
Intersection 0%
External services 0%
65%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 90%
Sewer Works 95%
Water & Gas Reticulation 100%
Conduit and AGI Installation _ 100%
Pavement Works 100%
Kerb & Channeling 100%
Electrical & NBN 20%
Footpaths & Top Soiling 0%
Asphalting and Line-marking 0%
Intersection 0%
External services 0%
35%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 90%
Sewer Works 90%
Water & Gas Reticulation 30%
Conduit and AGI Installation 0%
Pavement Works 0%
Kerb & Channeling 0%
Electrical & NBN 0%
Footpaths & Top Soiling 0%
Asphalting and Line-marking 0%
Intersection 0%
External services 0%
MARCH 2025 UPDATE