PURCHASER UPDATE
STAGE 1
STAGE 2
STAGE 3
STAGE 4
STAGE 5
STAGE 6
STAGE 7
COMPLETE
COMPLETE
COMPLETE
COMPLETE
100%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 100%
Sewer Works 100%
Water & Gas Reticulation 100%
Conduit and AGI Installation _ 100%
Pavement Works 100%
Kerb & Channeling _100%
Electrical & NBN 100%
Footpaths & Top Soiling _ 100%
Asphalting and Line-marking 50%
Intersection 0%
External services 0%
85%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 100%
Sewer Works 100%
Water & Gas Reticulation 100%
Conduit and AGI Installation _ 100%
Pavement Works 100%
Kerb & Channeling 100%
Electrical & NBN 100%
Footpaths & Top Soiling 100%
Asphalting and Line-marking 10%
Intersection 100%
External services 100%
55%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 100%
Sewer Works 100%
Water & Gas Reticulation 100%
Conduit and AGI Installation 100%
Pavement Works 50%
Kerb & Channeling 0%
Electrical & NBN 0%
Footpaths & Top Soiling 0%
Asphalting and Line-marking 0%
Intersection 0%
External services 0%
MAY 2025 UPDATE