PURCHASER UPDATE
STAGE 1
STAGE 2
STAGE 3
STAGE 4
STAGE 5
STAGE 6
STAGE 7
STAGE 8
COMPLETE
COMPLETE
98.5%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 100%
Sewer Works 100%
Water & Gas Reticulation 100%
Conduit and AGI Installation 100%
Pavement Works 100%
Kerb & Channeling 100%
Electrical & NBN 100%
Footpaths & Top Soiling 95%
Asphalting and Line-marking 95%
Intersection 95%
External services 100%
100%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 100%
Sewer Works 100%
Water & Gas Reticulation 100%
Conduit and AGI Installation 100%
Pavement Works 100%
Kerb & Channeling 100%
Electrical & NBN 100%
Footpaths & Top Soiling 100%
Asphalting and Line-marking 100%
Intersection 100%
External services 100%
56%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 90%
Sewer Works 95%
Water & Gas Reticulation 90%
Conduit and AGI Installation 100%
Pavement Works 60%
Kerb & Channeling 100%
Electrical & NBN 30%
Footpaths & Top Soiling 20%
Asphalting and Line-marking 0%
Intersection 0%
External services 0%
45%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 90%
Sewer Works 95%
Water & Gas Reticulation 80%
Conduit and AGI Installation 100%
Pavement Works 30%
Kerb & Channeling 0%
Electrical & NBN 0%
Footpaths & Top Soiling 0%
Asphalting and Line-marking 0%
Intersection 0%
External services 0%
22%
COMPLETE
Site Establishment 100%
Bulk Earthworks 100%
Drainage Works 50%
Sewer Works 35%
Water & Gas Reticulation 0%
Conduit and AGI Installation 0%
Pavement Works 0%
Kerb & Channeling 0%
Electrical & NBN 0%
Footpaths & Top Soiling 0%
Asphalting and Line-marking 0%
Intersection 0%
External services 0%
0%
COMPLETE
Site Establishment 0%
Bulk Earthworks 0%
Drainage Works 0%
Sewer Works 0%
Water & Gas Reticulation 0%
Conduit and AGI Installation 0%
Pavement Works 0%
Kerb & Channeling 0%
Electrical & NBN 0%
Footpaths & Top Soiling 0%
Asphalting and Line-marking 0%
Intersection 0%
External services 0%
DECEMBER 2024 UPDATE